How to change the order of summation?

The name of the pictureThe name of the pictureThe name of the pictureClash Royale CLAN TAG#URR8PPP











up vote
8
down vote

favorite
3












I have stumbled upon, multiple times, on cases where I need to change
the order of summation (usally of finite sums).



One problem I saw was simple
$$
sum_i=1^inftysum_j=i^inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
$$



and I can go from the first sum to the second by noting that the
constraints are
$$
1leq ileq j<infty
$$
so the first double sum does not constrain on $i$ and constrains
$j$ to $jgeq i$. The second double summation doesn't put any constrains
on $j$ but constrains $i$ relative to $j$ $(1leq ileq j)$.



While this approach works for simple examples such as this. I am having
problems using it where the bounds are more complicated.



The current problem interchanges the following
$$
sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k
$$



I started by writing
$$
kleq n-i+1
$$



and got
$$
ileq n-k+1
$$



but all other bounds are not clear to me..



the problem is that I can't use this technique since I can't write
the inequalities in the same form of
$$
1leq ileq f(j)leq n
$$



where $n$ is some bound (possibly $infty$).



My question is how to approach the second example by a technique that
should be able to handle similar cases







share|cite|improve this question


















  • 1




    The set of conditions $$1leqslant ileqslant n-1qquad 2leqslant kleqslant n-i+1qquad(ast)$$ must be transformed into conditions $$mleqslant kleqslant pqquad f(k)leqslant ileqslant g(k)qquad(circ)$$ for some $m$ and $p$ independent of $i$. First note that $igeqslant1$ hence every $k$ of interest is such that $$2leqslant kleqslant n$$ Now, for some fixed $k$, $(ast)$ reads $$1leqslant ileqslant n-1qquad ileqslant n-k+1$$ Since $kgeqslant2$, one is left with $$1leqslant ileqslant n-k+1$$ hence $(circ)$ reads $$2leqslant kleqslant nqquad1leqslant ileqslant n-k+1$$
    – Did
    Jul 31 '16 at 14:20














up vote
8
down vote

favorite
3












I have stumbled upon, multiple times, on cases where I need to change
the order of summation (usally of finite sums).



One problem I saw was simple
$$
sum_i=1^inftysum_j=i^inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
$$



and I can go from the first sum to the second by noting that the
constraints are
$$
1leq ileq j<infty
$$
so the first double sum does not constrain on $i$ and constrains
$j$ to $jgeq i$. The second double summation doesn't put any constrains
on $j$ but constrains $i$ relative to $j$ $(1leq ileq j)$.



While this approach works for simple examples such as this. I am having
problems using it where the bounds are more complicated.



The current problem interchanges the following
$$
sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k
$$



I started by writing
$$
kleq n-i+1
$$



and got
$$
ileq n-k+1
$$



but all other bounds are not clear to me..



the problem is that I can't use this technique since I can't write
the inequalities in the same form of
$$
1leq ileq f(j)leq n
$$



where $n$ is some bound (possibly $infty$).



My question is how to approach the second example by a technique that
should be able to handle similar cases







share|cite|improve this question


















  • 1




    The set of conditions $$1leqslant ileqslant n-1qquad 2leqslant kleqslant n-i+1qquad(ast)$$ must be transformed into conditions $$mleqslant kleqslant pqquad f(k)leqslant ileqslant g(k)qquad(circ)$$ for some $m$ and $p$ independent of $i$. First note that $igeqslant1$ hence every $k$ of interest is such that $$2leqslant kleqslant n$$ Now, for some fixed $k$, $(ast)$ reads $$1leqslant ileqslant n-1qquad ileqslant n-k+1$$ Since $kgeqslant2$, one is left with $$1leqslant ileqslant n-k+1$$ hence $(circ)$ reads $$2leqslant kleqslant nqquad1leqslant ileqslant n-k+1$$
    – Did
    Jul 31 '16 at 14:20












up vote
8
down vote

favorite
3









up vote
8
down vote

favorite
3






3





I have stumbled upon, multiple times, on cases where I need to change
the order of summation (usally of finite sums).



One problem I saw was simple
$$
sum_i=1^inftysum_j=i^inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
$$



and I can go from the first sum to the second by noting that the
constraints are
$$
1leq ileq j<infty
$$
so the first double sum does not constrain on $i$ and constrains
$j$ to $jgeq i$. The second double summation doesn't put any constrains
on $j$ but constrains $i$ relative to $j$ $(1leq ileq j)$.



While this approach works for simple examples such as this. I am having
problems using it where the bounds are more complicated.



The current problem interchanges the following
$$
sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k
$$



I started by writing
$$
kleq n-i+1
$$



and got
$$
ileq n-k+1
$$



but all other bounds are not clear to me..



the problem is that I can't use this technique since I can't write
the inequalities in the same form of
$$
1leq ileq f(j)leq n
$$



where $n$ is some bound (possibly $infty$).



My question is how to approach the second example by a technique that
should be able to handle similar cases







share|cite|improve this question














I have stumbled upon, multiple times, on cases where I need to change
the order of summation (usally of finite sums).



One problem I saw was simple
$$
sum_i=1^inftysum_j=i^inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
$$



and I can go from the first sum to the second by noting that the
constraints are
$$
1leq ileq j<infty
$$
so the first double sum does not constrain on $i$ and constrains
$j$ to $jgeq i$. The second double summation doesn't put any constrains
on $j$ but constrains $i$ relative to $j$ $(1leq ileq j)$.



While this approach works for simple examples such as this. I am having
problems using it where the bounds are more complicated.



The current problem interchanges the following
$$
sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k
$$



I started by writing
$$
kleq n-i+1
$$



and got
$$
ileq n-k+1
$$



but all other bounds are not clear to me..



the problem is that I can't use this technique since I can't write
the inequalities in the same form of
$$
1leq ileq f(j)leq n
$$



where $n$ is some bound (possibly $infty$).



My question is how to approach the second example by a technique that
should be able to handle similar cases









share|cite|improve this question













share|cite|improve this question




share|cite|improve this question








edited Aug 28 at 15:09









Narendra Deconda

248




248










asked Jul 31 '16 at 13:09









Belgi

14.3k651105




14.3k651105







  • 1




    The set of conditions $$1leqslant ileqslant n-1qquad 2leqslant kleqslant n-i+1qquad(ast)$$ must be transformed into conditions $$mleqslant kleqslant pqquad f(k)leqslant ileqslant g(k)qquad(circ)$$ for some $m$ and $p$ independent of $i$. First note that $igeqslant1$ hence every $k$ of interest is such that $$2leqslant kleqslant n$$ Now, for some fixed $k$, $(ast)$ reads $$1leqslant ileqslant n-1qquad ileqslant n-k+1$$ Since $kgeqslant2$, one is left with $$1leqslant ileqslant n-k+1$$ hence $(circ)$ reads $$2leqslant kleqslant nqquad1leqslant ileqslant n-k+1$$
    – Did
    Jul 31 '16 at 14:20












  • 1




    The set of conditions $$1leqslant ileqslant n-1qquad 2leqslant kleqslant n-i+1qquad(ast)$$ must be transformed into conditions $$mleqslant kleqslant pqquad f(k)leqslant ileqslant g(k)qquad(circ)$$ for some $m$ and $p$ independent of $i$. First note that $igeqslant1$ hence every $k$ of interest is such that $$2leqslant kleqslant n$$ Now, for some fixed $k$, $(ast)$ reads $$1leqslant ileqslant n-1qquad ileqslant n-k+1$$ Since $kgeqslant2$, one is left with $$1leqslant ileqslant n-k+1$$ hence $(circ)$ reads $$2leqslant kleqslant nqquad1leqslant ileqslant n-k+1$$
    – Did
    Jul 31 '16 at 14:20







1




1




The set of conditions $$1leqslant ileqslant n-1qquad 2leqslant kleqslant n-i+1qquad(ast)$$ must be transformed into conditions $$mleqslant kleqslant pqquad f(k)leqslant ileqslant g(k)qquad(circ)$$ for some $m$ and $p$ independent of $i$. First note that $igeqslant1$ hence every $k$ of interest is such that $$2leqslant kleqslant n$$ Now, for some fixed $k$, $(ast)$ reads $$1leqslant ileqslant n-1qquad ileqslant n-k+1$$ Since $kgeqslant2$, one is left with $$1leqslant ileqslant n-k+1$$ hence $(circ)$ reads $$2leqslant kleqslant nqquad1leqslant ileqslant n-k+1$$
– Did
Jul 31 '16 at 14:20




The set of conditions $$1leqslant ileqslant n-1qquad 2leqslant kleqslant n-i+1qquad(ast)$$ must be transformed into conditions $$mleqslant kleqslant pqquad f(k)leqslant ileqslant g(k)qquad(circ)$$ for some $m$ and $p$ independent of $i$. First note that $igeqslant1$ hence every $k$ of interest is such that $$2leqslant kleqslant n$$ Now, for some fixed $k$, $(ast)$ reads $$1leqslant ileqslant n-1qquad ileqslant n-k+1$$ Since $kgeqslant2$, one is left with $$1leqslant ileqslant n-k+1$$ hence $(circ)$ reads $$2leqslant kleqslant nqquad1leqslant ileqslant n-k+1$$
– Did
Jul 31 '16 at 14:20










5 Answers
5






active

oldest

votes

















up vote
5
down vote













Changing the order in the first double sum is manageable. We could therefore use it as some kind of prototype. We transform the second double sum, so that the index range is similar to the first one.




first double sum:



The following presentation of the index range might be helpful.
beginalign*
sum_i=1^inftysum_j=i^inftyf(i,j)=sum_colorblue1leq ileq j<inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
endalign*
If we focus at the middle double sum and look at the index range $1leq ileq j<infty$ we observe the left-hand side as well as the right-hand side can be easily derived.




We do some rearrangements to derive a similar representation in the




second double sum:



We obtain
beginalign*
sum_i=1^n-1sum_k=2^n-i+1g(i,k)&=sum_i=1^n-1sum_k=2^i+1g(n-i,k)tag1\
&=sum_i=1^n-1sum_k=1^ig(n-i,k+1)tag2\
&=sum_1leq kleq ileq n-1g(n-i,k+1)tag3\
&=sum_k=1^n-1sum_i=k^n-1g(n-i,k+1)tag4
endalign*




Comment:



  • In (1) we change the order of the first sum $irightarrow n-i$. Note, that reversing the order this way
    beginalign*
    sum_i=1^n-1a(i)&=a(1)+a(2)+cdots+a(n-1)\
    &=a(n-1)+a(n-2)+cdots+a(1)\
    &=sum_i=1^n-1a(n-i)
    endalign*
    does not change the lower and upper index of $i$, but each occurrence of $i$ within the sum has to be substituted with $n-i$. So, we replace $a(i)$ with $a(n-i)$.

  • In (2) we shift the index $k$ by one, so that we also can start with $k=1$.


  • In (3) we write the double sum as we did in the first case.


  • In (4) it's easy to change the order of the double sum based upon the representation in (3).






share|cite|improve this answer






















  • The change of variable $ito n-i$ is unnecessary and probably too much ad hoc to be fully commendable. // In (4) the sum on $i$ goes from $i=k$ to $n-1$, not $n-i$.
    – Did
    Jul 31 '16 at 14:24










  • @Did: Thanks for the hint. Typo at the end corrected. The idea to change the order $irightarrow n-i$ was to derive an index range in (3) which is as close as possible to the index range of the first double sum. But of course this is clear to you. :-)
    – Markus Scheuer
    Jul 31 '16 at 14:31










  • Thank you for your answer, can you please add details about the first change ? I didn't manage to understand how this change left the first outer sum unchanged (since we changed $i$)
    – Belgi
    Jul 31 '16 at 18:53










  • @Belgi: You're welcome. I've added an explanation in the comment section. Regards,
    – Markus Scheuer
    Jul 31 '16 at 19:10

















up vote
5
down vote













I solve this kind of problem with the following steps:



  1. Draw a plane i-k (in general is over your dummy index, remember this index can be called as you want). You'll find the conditions over the sum generates a triangle, in this case.

  2. The last step is to try to generate the last graphic changing the order of the sum,i.e., if your first sum is over i, now this index will be the last, so your first sum is over k in this case when you change the order.

Well with this steps you'll find the same answer you put in the description. I couldn't do it at this moment with graphics to show you, I encourage you to try it uniquely following this steps.






share|cite|improve this answer





























    up vote
    2
    down vote













    You can look at it this way: you're looking to sum all the following terms:



    $$beginmatrix
    &i&1&2&3&4&cdots&n-2&n-1\
    k\
    2&&(1,2)&(2,2)&cdots&cdots&cdots&(n-2,2)&(n-1,2)\
    3&&(1,3)&(2,3)&cdots&cdots&cdots&(n-2,3)\
    4&&(1,4)&(2,4)\
    5&&(1,5)&(2,5)\
    vdots&&vdots&vdots&\
    &&vdots&(2,n-1)\
    n&&(1,n)
    endmatrix$$



    The first way you wrote it corresponds to summing the terms column by column, then adding those sums up. To turn it into the second form, you'll have to add the terms of each row then add them all up. The bound on $i$ becomes $1leq i leq n- k+1$ as for $k$: $2leq kleq n$.



    Also, as you wrote, we have $2leq kleq n-i+1$, the maximum value for $k$ is reached when $i=1$, so $2leq kleq n$. As for the bounds on $i$ you have already found them!






    share|cite|improve this answer



























      up vote
      1
      down vote













      The double sum implements the contraints



      $$1le ile n-1,\2le kle n-i+1.$$



      Substituting the extreme values of $i$, you obtain the possible extreme values of $k$



      $$2le kle max(n-1+1,n-(n-1)+1)$$ or



      $$2le kle n.$$



      Then if you fix $k$ and express $i$ in terms of it, you get the constraint



      $$ile n-k+1,$$ which you combine with the range



      $$1le ilemin(n-k+1,n-1)=n-k+1.$$



      So



      $$sum_k=2^nsum_i=1^n-k+1$$




      Similarly in the first case,



      $$1le i,\ile j.$$



      The range of $j$ is $1le j$, and with $j$ fixed, $1le ile j$, giving



      $$sum_j=1^inftysum_i=j^infty.$$






      share|cite|improve this answer



























        up vote
        0
        down vote













        I've found the Iverson bracket extremely useful for this sort of calculation. For a reference on the technique, I learned it from Concrete Mathematics



        The Iverson bracket is a function whose argument is a proposition, and is defined by the formula



        $$ [P] = begincases 0 & P text is false \ 1 & P text is true endcases $$



        You use this to express summations, such as



        $$ sum_n=a^b f(n) = sum_n in mathbbZ [a leq n leq b] f(n) $$



        When using this technique, you generally take all sums to be over all integers and use the Iverson brackets to control which terms are actually summed over. I will henceforth suppress the $in mathbbZ$.



        It's additionally useful to use the convention that when $P$ is false, that $[P]$ is strongly zero; that is, when P is false, we always say $[P] t = 0$ no matter what $t$ is, even when $t$ is undefined. As an example of this usage:



        $$ fracpi^26 = sum_n [n geq 1] frac1n^2 $$



        Normally we would say the right hand side is undefined, since $frac1n^2$ is undefined when $n=0$. But by the "strongly zero" convention, we say that $[n geq 1] frac1n^2$ is well-defined and zero when $n=0$, so this sum makes sense.




        Now, to apply it to your example:




        $$sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k$$




        $$sum_i=1^n-1sum_k=2^n-i+1
        = sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



        Note that $[P][Q] = [P text and Q]$. Multiplication is somewhat more convenient notation, though, so I leave it expressed as a product.



        One could approach this problem by finding a different way of expressing this system of inequalities. We can rewrite them as



        $$ 1 leq i qquad i leq n-1 qquad qquad 2 leq k qquad qquad i leq n+1-k $$



        The $i leq n-1$ condition is redundant. Having "solved" the last inequality for $i$ it's clear that we can rewrite



        $$ [1 leq i leq n-1] [2 leq k leq n-i+1] = [2 leq k] [1 leq i leq n+1-k] $$



        Depending on our purposes, it may help to observe the implicit $1 leq n+1-k$ constraint and solve it for $k$ to make it more explicit, so we have



        $$ ldots = [2 leq k leq n] [1 leq i leq n+1-k] $$



        It's clear now that



        $$ sum_i,k [2 leq k leq n] [1 leq i leq n+1-k] = sum_k=2^n sum_i=1^n+1-k $$



        if we really want to rewrite the summation back into this form.




        One way in which this notation becomes really useful, in my opinion, when you consider changing variables. If I was given



        $$ sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



        I would often consider simplifying the upper bound by making a substitution $j = n-i+1$ (or $i = n-j+1$), replacing the sum over $i$ with a sum over $j$



        $$ ldots = sum_j,k [1 leq n-j+1 leq n-1] [2 leq k leq j]
        \= sum_j,k [1 leq n-j+1] [n-j+1 leq n-1] [2 leq k leq j]
        \= sum_j,k [j leq n] [2 leq j] [2 leq k leq j]
        \= sum_j,k [2 leq k leq j leq n] $$



        which makes it easy to see other ways to rewrite this. E.g. if I wanted to sum over $k$ first, it's clear this becomes



        $$ ldots = sum_j,k [2 leq k leq n] [k leq j leq n]
        \= sum_k=2^n sum_j=k^n $$



        Or I could change $j$ back to $i$ first if I wanted.






        share|cite|improve this answer






















          Your Answer




          StackExchange.ifUsing("editor", function ()
          return StackExchange.using("mathjaxEditing", function ()
          StackExchange.MarkdownEditor.creationCallbacks.add(function (editor, postfix)
          StackExchange.mathjaxEditing.prepareWmdForMathJax(editor, postfix, [["$", "$"], ["\\(","\\)"]]);
          );
          );
          , "mathjax-editing");

          StackExchange.ready(function()
          var channelOptions =
          tags: "".split(" "),
          id: "69"
          ;
          initTagRenderer("".split(" "), "".split(" "), channelOptions);

          StackExchange.using("externalEditor", function()
          // Have to fire editor after snippets, if snippets enabled
          if (StackExchange.settings.snippets.snippetsEnabled)
          StackExchange.using("snippets", function()
          createEditor();
          );

          else
          createEditor();

          );

          function createEditor()
          StackExchange.prepareEditor(
          heartbeatType: 'answer',
          convertImagesToLinks: true,
          noModals: false,
          showLowRepImageUploadWarning: true,
          reputationToPostImages: 10,
          bindNavPrevention: true,
          postfix: "",
          noCode: true, onDemand: true,
          discardSelector: ".discard-answer"
          ,immediatelyShowMarkdownHelp:true
          );



          );













           

          draft saved


          draft discarded


















          StackExchange.ready(
          function ()
          StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f1876828%2fhow-to-change-the-order-of-summation%23new-answer', 'question_page');

          );

          Post as a guest






























          5 Answers
          5






          active

          oldest

          votes








          5 Answers
          5






          active

          oldest

          votes









          active

          oldest

          votes






          active

          oldest

          votes








          up vote
          5
          down vote













          Changing the order in the first double sum is manageable. We could therefore use it as some kind of prototype. We transform the second double sum, so that the index range is similar to the first one.




          first double sum:



          The following presentation of the index range might be helpful.
          beginalign*
          sum_i=1^inftysum_j=i^inftyf(i,j)=sum_colorblue1leq ileq j<inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
          endalign*
          If we focus at the middle double sum and look at the index range $1leq ileq j<infty$ we observe the left-hand side as well as the right-hand side can be easily derived.




          We do some rearrangements to derive a similar representation in the




          second double sum:



          We obtain
          beginalign*
          sum_i=1^n-1sum_k=2^n-i+1g(i,k)&=sum_i=1^n-1sum_k=2^i+1g(n-i,k)tag1\
          &=sum_i=1^n-1sum_k=1^ig(n-i,k+1)tag2\
          &=sum_1leq kleq ileq n-1g(n-i,k+1)tag3\
          &=sum_k=1^n-1sum_i=k^n-1g(n-i,k+1)tag4
          endalign*




          Comment:



          • In (1) we change the order of the first sum $irightarrow n-i$. Note, that reversing the order this way
            beginalign*
            sum_i=1^n-1a(i)&=a(1)+a(2)+cdots+a(n-1)\
            &=a(n-1)+a(n-2)+cdots+a(1)\
            &=sum_i=1^n-1a(n-i)
            endalign*
            does not change the lower and upper index of $i$, but each occurrence of $i$ within the sum has to be substituted with $n-i$. So, we replace $a(i)$ with $a(n-i)$.

          • In (2) we shift the index $k$ by one, so that we also can start with $k=1$.


          • In (3) we write the double sum as we did in the first case.


          • In (4) it's easy to change the order of the double sum based upon the representation in (3).






          share|cite|improve this answer






















          • The change of variable $ito n-i$ is unnecessary and probably too much ad hoc to be fully commendable. // In (4) the sum on $i$ goes from $i=k$ to $n-1$, not $n-i$.
            – Did
            Jul 31 '16 at 14:24










          • @Did: Thanks for the hint. Typo at the end corrected. The idea to change the order $irightarrow n-i$ was to derive an index range in (3) which is as close as possible to the index range of the first double sum. But of course this is clear to you. :-)
            – Markus Scheuer
            Jul 31 '16 at 14:31










          • Thank you for your answer, can you please add details about the first change ? I didn't manage to understand how this change left the first outer sum unchanged (since we changed $i$)
            – Belgi
            Jul 31 '16 at 18:53










          • @Belgi: You're welcome. I've added an explanation in the comment section. Regards,
            – Markus Scheuer
            Jul 31 '16 at 19:10














          up vote
          5
          down vote













          Changing the order in the first double sum is manageable. We could therefore use it as some kind of prototype. We transform the second double sum, so that the index range is similar to the first one.




          first double sum:



          The following presentation of the index range might be helpful.
          beginalign*
          sum_i=1^inftysum_j=i^inftyf(i,j)=sum_colorblue1leq ileq j<inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
          endalign*
          If we focus at the middle double sum and look at the index range $1leq ileq j<infty$ we observe the left-hand side as well as the right-hand side can be easily derived.




          We do some rearrangements to derive a similar representation in the




          second double sum:



          We obtain
          beginalign*
          sum_i=1^n-1sum_k=2^n-i+1g(i,k)&=sum_i=1^n-1sum_k=2^i+1g(n-i,k)tag1\
          &=sum_i=1^n-1sum_k=1^ig(n-i,k+1)tag2\
          &=sum_1leq kleq ileq n-1g(n-i,k+1)tag3\
          &=sum_k=1^n-1sum_i=k^n-1g(n-i,k+1)tag4
          endalign*




          Comment:



          • In (1) we change the order of the first sum $irightarrow n-i$. Note, that reversing the order this way
            beginalign*
            sum_i=1^n-1a(i)&=a(1)+a(2)+cdots+a(n-1)\
            &=a(n-1)+a(n-2)+cdots+a(1)\
            &=sum_i=1^n-1a(n-i)
            endalign*
            does not change the lower and upper index of $i$, but each occurrence of $i$ within the sum has to be substituted with $n-i$. So, we replace $a(i)$ with $a(n-i)$.

          • In (2) we shift the index $k$ by one, so that we also can start with $k=1$.


          • In (3) we write the double sum as we did in the first case.


          • In (4) it's easy to change the order of the double sum based upon the representation in (3).






          share|cite|improve this answer






















          • The change of variable $ito n-i$ is unnecessary and probably too much ad hoc to be fully commendable. // In (4) the sum on $i$ goes from $i=k$ to $n-1$, not $n-i$.
            – Did
            Jul 31 '16 at 14:24










          • @Did: Thanks for the hint. Typo at the end corrected. The idea to change the order $irightarrow n-i$ was to derive an index range in (3) which is as close as possible to the index range of the first double sum. But of course this is clear to you. :-)
            – Markus Scheuer
            Jul 31 '16 at 14:31










          • Thank you for your answer, can you please add details about the first change ? I didn't manage to understand how this change left the first outer sum unchanged (since we changed $i$)
            – Belgi
            Jul 31 '16 at 18:53










          • @Belgi: You're welcome. I've added an explanation in the comment section. Regards,
            – Markus Scheuer
            Jul 31 '16 at 19:10












          up vote
          5
          down vote










          up vote
          5
          down vote









          Changing the order in the first double sum is manageable. We could therefore use it as some kind of prototype. We transform the second double sum, so that the index range is similar to the first one.




          first double sum:



          The following presentation of the index range might be helpful.
          beginalign*
          sum_i=1^inftysum_j=i^inftyf(i,j)=sum_colorblue1leq ileq j<inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
          endalign*
          If we focus at the middle double sum and look at the index range $1leq ileq j<infty$ we observe the left-hand side as well as the right-hand side can be easily derived.




          We do some rearrangements to derive a similar representation in the




          second double sum:



          We obtain
          beginalign*
          sum_i=1^n-1sum_k=2^n-i+1g(i,k)&=sum_i=1^n-1sum_k=2^i+1g(n-i,k)tag1\
          &=sum_i=1^n-1sum_k=1^ig(n-i,k+1)tag2\
          &=sum_1leq kleq ileq n-1g(n-i,k+1)tag3\
          &=sum_k=1^n-1sum_i=k^n-1g(n-i,k+1)tag4
          endalign*




          Comment:



          • In (1) we change the order of the first sum $irightarrow n-i$. Note, that reversing the order this way
            beginalign*
            sum_i=1^n-1a(i)&=a(1)+a(2)+cdots+a(n-1)\
            &=a(n-1)+a(n-2)+cdots+a(1)\
            &=sum_i=1^n-1a(n-i)
            endalign*
            does not change the lower and upper index of $i$, but each occurrence of $i$ within the sum has to be substituted with $n-i$. So, we replace $a(i)$ with $a(n-i)$.

          • In (2) we shift the index $k$ by one, so that we also can start with $k=1$.


          • In (3) we write the double sum as we did in the first case.


          • In (4) it's easy to change the order of the double sum based upon the representation in (3).






          share|cite|improve this answer














          Changing the order in the first double sum is manageable. We could therefore use it as some kind of prototype. We transform the second double sum, so that the index range is similar to the first one.




          first double sum:



          The following presentation of the index range might be helpful.
          beginalign*
          sum_i=1^inftysum_j=i^inftyf(i,j)=sum_colorblue1leq ileq j<inftyf(i,j)=sum_j=1^inftysum_i=1^jf(i,j)
          endalign*
          If we focus at the middle double sum and look at the index range $1leq ileq j<infty$ we observe the left-hand side as well as the right-hand side can be easily derived.




          We do some rearrangements to derive a similar representation in the




          second double sum:



          We obtain
          beginalign*
          sum_i=1^n-1sum_k=2^n-i+1g(i,k)&=sum_i=1^n-1sum_k=2^i+1g(n-i,k)tag1\
          &=sum_i=1^n-1sum_k=1^ig(n-i,k+1)tag2\
          &=sum_1leq kleq ileq n-1g(n-i,k+1)tag3\
          &=sum_k=1^n-1sum_i=k^n-1g(n-i,k+1)tag4
          endalign*




          Comment:



          • In (1) we change the order of the first sum $irightarrow n-i$. Note, that reversing the order this way
            beginalign*
            sum_i=1^n-1a(i)&=a(1)+a(2)+cdots+a(n-1)\
            &=a(n-1)+a(n-2)+cdots+a(1)\
            &=sum_i=1^n-1a(n-i)
            endalign*
            does not change the lower and upper index of $i$, but each occurrence of $i$ within the sum has to be substituted with $n-i$. So, we replace $a(i)$ with $a(n-i)$.

          • In (2) we shift the index $k$ by one, so that we also can start with $k=1$.


          • In (3) we write the double sum as we did in the first case.


          • In (4) it's easy to change the order of the double sum based upon the representation in (3).







          share|cite|improve this answer














          share|cite|improve this answer



          share|cite|improve this answer








          edited Jul 4 at 17:18

























          answered Jul 31 '16 at 14:08









          Markus Scheuer

          57k452136




          57k452136











          • The change of variable $ito n-i$ is unnecessary and probably too much ad hoc to be fully commendable. // In (4) the sum on $i$ goes from $i=k$ to $n-1$, not $n-i$.
            – Did
            Jul 31 '16 at 14:24










          • @Did: Thanks for the hint. Typo at the end corrected. The idea to change the order $irightarrow n-i$ was to derive an index range in (3) which is as close as possible to the index range of the first double sum. But of course this is clear to you. :-)
            – Markus Scheuer
            Jul 31 '16 at 14:31










          • Thank you for your answer, can you please add details about the first change ? I didn't manage to understand how this change left the first outer sum unchanged (since we changed $i$)
            – Belgi
            Jul 31 '16 at 18:53










          • @Belgi: You're welcome. I've added an explanation in the comment section. Regards,
            – Markus Scheuer
            Jul 31 '16 at 19:10
















          • The change of variable $ito n-i$ is unnecessary and probably too much ad hoc to be fully commendable. // In (4) the sum on $i$ goes from $i=k$ to $n-1$, not $n-i$.
            – Did
            Jul 31 '16 at 14:24










          • @Did: Thanks for the hint. Typo at the end corrected. The idea to change the order $irightarrow n-i$ was to derive an index range in (3) which is as close as possible to the index range of the first double sum. But of course this is clear to you. :-)
            – Markus Scheuer
            Jul 31 '16 at 14:31










          • Thank you for your answer, can you please add details about the first change ? I didn't manage to understand how this change left the first outer sum unchanged (since we changed $i$)
            – Belgi
            Jul 31 '16 at 18:53










          • @Belgi: You're welcome. I've added an explanation in the comment section. Regards,
            – Markus Scheuer
            Jul 31 '16 at 19:10















          The change of variable $ito n-i$ is unnecessary and probably too much ad hoc to be fully commendable. // In (4) the sum on $i$ goes from $i=k$ to $n-1$, not $n-i$.
          – Did
          Jul 31 '16 at 14:24




          The change of variable $ito n-i$ is unnecessary and probably too much ad hoc to be fully commendable. // In (4) the sum on $i$ goes from $i=k$ to $n-1$, not $n-i$.
          – Did
          Jul 31 '16 at 14:24












          @Did: Thanks for the hint. Typo at the end corrected. The idea to change the order $irightarrow n-i$ was to derive an index range in (3) which is as close as possible to the index range of the first double sum. But of course this is clear to you. :-)
          – Markus Scheuer
          Jul 31 '16 at 14:31




          @Did: Thanks for the hint. Typo at the end corrected. The idea to change the order $irightarrow n-i$ was to derive an index range in (3) which is as close as possible to the index range of the first double sum. But of course this is clear to you. :-)
          – Markus Scheuer
          Jul 31 '16 at 14:31












          Thank you for your answer, can you please add details about the first change ? I didn't manage to understand how this change left the first outer sum unchanged (since we changed $i$)
          – Belgi
          Jul 31 '16 at 18:53




          Thank you for your answer, can you please add details about the first change ? I didn't manage to understand how this change left the first outer sum unchanged (since we changed $i$)
          – Belgi
          Jul 31 '16 at 18:53












          @Belgi: You're welcome. I've added an explanation in the comment section. Regards,
          – Markus Scheuer
          Jul 31 '16 at 19:10




          @Belgi: You're welcome. I've added an explanation in the comment section. Regards,
          – Markus Scheuer
          Jul 31 '16 at 19:10










          up vote
          5
          down vote













          I solve this kind of problem with the following steps:



          1. Draw a plane i-k (in general is over your dummy index, remember this index can be called as you want). You'll find the conditions over the sum generates a triangle, in this case.

          2. The last step is to try to generate the last graphic changing the order of the sum,i.e., if your first sum is over i, now this index will be the last, so your first sum is over k in this case when you change the order.

          Well with this steps you'll find the same answer you put in the description. I couldn't do it at this moment with graphics to show you, I encourage you to try it uniquely following this steps.






          share|cite|improve this answer


























            up vote
            5
            down vote













            I solve this kind of problem with the following steps:



            1. Draw a plane i-k (in general is over your dummy index, remember this index can be called as you want). You'll find the conditions over the sum generates a triangle, in this case.

            2. The last step is to try to generate the last graphic changing the order of the sum,i.e., if your first sum is over i, now this index will be the last, so your first sum is over k in this case when you change the order.

            Well with this steps you'll find the same answer you put in the description. I couldn't do it at this moment with graphics to show you, I encourage you to try it uniquely following this steps.






            share|cite|improve this answer
























              up vote
              5
              down vote










              up vote
              5
              down vote









              I solve this kind of problem with the following steps:



              1. Draw a plane i-k (in general is over your dummy index, remember this index can be called as you want). You'll find the conditions over the sum generates a triangle, in this case.

              2. The last step is to try to generate the last graphic changing the order of the sum,i.e., if your first sum is over i, now this index will be the last, so your first sum is over k in this case when you change the order.

              Well with this steps you'll find the same answer you put in the description. I couldn't do it at this moment with graphics to show you, I encourage you to try it uniquely following this steps.






              share|cite|improve this answer














              I solve this kind of problem with the following steps:



              1. Draw a plane i-k (in general is over your dummy index, remember this index can be called as you want). You'll find the conditions over the sum generates a triangle, in this case.

              2. The last step is to try to generate the last graphic changing the order of the sum,i.e., if your first sum is over i, now this index will be the last, so your first sum is over k in this case when you change the order.

              Well with this steps you'll find the same answer you put in the description. I couldn't do it at this moment with graphics to show you, I encourage you to try it uniquely following this steps.







              share|cite|improve this answer














              share|cite|improve this answer



              share|cite|improve this answer








              edited Aug 28 at 16:07









              Narendra Deconda

              248




              248










              answered Jul 31 '16 at 13:31









              7919

              613




              613




















                  up vote
                  2
                  down vote













                  You can look at it this way: you're looking to sum all the following terms:



                  $$beginmatrix
                  &i&1&2&3&4&cdots&n-2&n-1\
                  k\
                  2&&(1,2)&(2,2)&cdots&cdots&cdots&(n-2,2)&(n-1,2)\
                  3&&(1,3)&(2,3)&cdots&cdots&cdots&(n-2,3)\
                  4&&(1,4)&(2,4)\
                  5&&(1,5)&(2,5)\
                  vdots&&vdots&vdots&\
                  &&vdots&(2,n-1)\
                  n&&(1,n)
                  endmatrix$$



                  The first way you wrote it corresponds to summing the terms column by column, then adding those sums up. To turn it into the second form, you'll have to add the terms of each row then add them all up. The bound on $i$ becomes $1leq i leq n- k+1$ as for $k$: $2leq kleq n$.



                  Also, as you wrote, we have $2leq kleq n-i+1$, the maximum value for $k$ is reached when $i=1$, so $2leq kleq n$. As for the bounds on $i$ you have already found them!






                  share|cite|improve this answer
























                    up vote
                    2
                    down vote













                    You can look at it this way: you're looking to sum all the following terms:



                    $$beginmatrix
                    &i&1&2&3&4&cdots&n-2&n-1\
                    k\
                    2&&(1,2)&(2,2)&cdots&cdots&cdots&(n-2,2)&(n-1,2)\
                    3&&(1,3)&(2,3)&cdots&cdots&cdots&(n-2,3)\
                    4&&(1,4)&(2,4)\
                    5&&(1,5)&(2,5)\
                    vdots&&vdots&vdots&\
                    &&vdots&(2,n-1)\
                    n&&(1,n)
                    endmatrix$$



                    The first way you wrote it corresponds to summing the terms column by column, then adding those sums up. To turn it into the second form, you'll have to add the terms of each row then add them all up. The bound on $i$ becomes $1leq i leq n- k+1$ as for $k$: $2leq kleq n$.



                    Also, as you wrote, we have $2leq kleq n-i+1$, the maximum value for $k$ is reached when $i=1$, so $2leq kleq n$. As for the bounds on $i$ you have already found them!






                    share|cite|improve this answer






















                      up vote
                      2
                      down vote










                      up vote
                      2
                      down vote









                      You can look at it this way: you're looking to sum all the following terms:



                      $$beginmatrix
                      &i&1&2&3&4&cdots&n-2&n-1\
                      k\
                      2&&(1,2)&(2,2)&cdots&cdots&cdots&(n-2,2)&(n-1,2)\
                      3&&(1,3)&(2,3)&cdots&cdots&cdots&(n-2,3)\
                      4&&(1,4)&(2,4)\
                      5&&(1,5)&(2,5)\
                      vdots&&vdots&vdots&\
                      &&vdots&(2,n-1)\
                      n&&(1,n)
                      endmatrix$$



                      The first way you wrote it corresponds to summing the terms column by column, then adding those sums up. To turn it into the second form, you'll have to add the terms of each row then add them all up. The bound on $i$ becomes $1leq i leq n- k+1$ as for $k$: $2leq kleq n$.



                      Also, as you wrote, we have $2leq kleq n-i+1$, the maximum value for $k$ is reached when $i=1$, so $2leq kleq n$. As for the bounds on $i$ you have already found them!






                      share|cite|improve this answer












                      You can look at it this way: you're looking to sum all the following terms:



                      $$beginmatrix
                      &i&1&2&3&4&cdots&n-2&n-1\
                      k\
                      2&&(1,2)&(2,2)&cdots&cdots&cdots&(n-2,2)&(n-1,2)\
                      3&&(1,3)&(2,3)&cdots&cdots&cdots&(n-2,3)\
                      4&&(1,4)&(2,4)\
                      5&&(1,5)&(2,5)\
                      vdots&&vdots&vdots&\
                      &&vdots&(2,n-1)\
                      n&&(1,n)
                      endmatrix$$



                      The first way you wrote it corresponds to summing the terms column by column, then adding those sums up. To turn it into the second form, you'll have to add the terms of each row then add them all up. The bound on $i$ becomes $1leq i leq n- k+1$ as for $k$: $2leq kleq n$.



                      Also, as you wrote, we have $2leq kleq n-i+1$, the maximum value for $k$ is reached when $i=1$, so $2leq kleq n$. As for the bounds on $i$ you have already found them!







                      share|cite|improve this answer












                      share|cite|improve this answer



                      share|cite|improve this answer










                      answered Jul 31 '16 at 13:31









                      GeorgSaliba

                      3,6861026




                      3,6861026




















                          up vote
                          1
                          down vote













                          The double sum implements the contraints



                          $$1le ile n-1,\2le kle n-i+1.$$



                          Substituting the extreme values of $i$, you obtain the possible extreme values of $k$



                          $$2le kle max(n-1+1,n-(n-1)+1)$$ or



                          $$2le kle n.$$



                          Then if you fix $k$ and express $i$ in terms of it, you get the constraint



                          $$ile n-k+1,$$ which you combine with the range



                          $$1le ilemin(n-k+1,n-1)=n-k+1.$$



                          So



                          $$sum_k=2^nsum_i=1^n-k+1$$




                          Similarly in the first case,



                          $$1le i,\ile j.$$



                          The range of $j$ is $1le j$, and with $j$ fixed, $1le ile j$, giving



                          $$sum_j=1^inftysum_i=j^infty.$$






                          share|cite|improve this answer
























                            up vote
                            1
                            down vote













                            The double sum implements the contraints



                            $$1le ile n-1,\2le kle n-i+1.$$



                            Substituting the extreme values of $i$, you obtain the possible extreme values of $k$



                            $$2le kle max(n-1+1,n-(n-1)+1)$$ or



                            $$2le kle n.$$



                            Then if you fix $k$ and express $i$ in terms of it, you get the constraint



                            $$ile n-k+1,$$ which you combine with the range



                            $$1le ilemin(n-k+1,n-1)=n-k+1.$$



                            So



                            $$sum_k=2^nsum_i=1^n-k+1$$




                            Similarly in the first case,



                            $$1le i,\ile j.$$



                            The range of $j$ is $1le j$, and with $j$ fixed, $1le ile j$, giving



                            $$sum_j=1^inftysum_i=j^infty.$$






                            share|cite|improve this answer






















                              up vote
                              1
                              down vote










                              up vote
                              1
                              down vote









                              The double sum implements the contraints



                              $$1le ile n-1,\2le kle n-i+1.$$



                              Substituting the extreme values of $i$, you obtain the possible extreme values of $k$



                              $$2le kle max(n-1+1,n-(n-1)+1)$$ or



                              $$2le kle n.$$



                              Then if you fix $k$ and express $i$ in terms of it, you get the constraint



                              $$ile n-k+1,$$ which you combine with the range



                              $$1le ilemin(n-k+1,n-1)=n-k+1.$$



                              So



                              $$sum_k=2^nsum_i=1^n-k+1$$




                              Similarly in the first case,



                              $$1le i,\ile j.$$



                              The range of $j$ is $1le j$, and with $j$ fixed, $1le ile j$, giving



                              $$sum_j=1^inftysum_i=j^infty.$$






                              share|cite|improve this answer












                              The double sum implements the contraints



                              $$1le ile n-1,\2le kle n-i+1.$$



                              Substituting the extreme values of $i$, you obtain the possible extreme values of $k$



                              $$2le kle max(n-1+1,n-(n-1)+1)$$ or



                              $$2le kle n.$$



                              Then if you fix $k$ and express $i$ in terms of it, you get the constraint



                              $$ile n-k+1,$$ which you combine with the range



                              $$1le ilemin(n-k+1,n-1)=n-k+1.$$



                              So



                              $$sum_k=2^nsum_i=1^n-k+1$$




                              Similarly in the first case,



                              $$1le i,\ile j.$$



                              The range of $j$ is $1le j$, and with $j$ fixed, $1le ile j$, giving



                              $$sum_j=1^inftysum_i=j^infty.$$







                              share|cite|improve this answer












                              share|cite|improve this answer



                              share|cite|improve this answer










                              answered Jul 31 '16 at 14:45









                              Yves Daoust

                              113k665208




                              113k665208




















                                  up vote
                                  0
                                  down vote













                                  I've found the Iverson bracket extremely useful for this sort of calculation. For a reference on the technique, I learned it from Concrete Mathematics



                                  The Iverson bracket is a function whose argument is a proposition, and is defined by the formula



                                  $$ [P] = begincases 0 & P text is false \ 1 & P text is true endcases $$



                                  You use this to express summations, such as



                                  $$ sum_n=a^b f(n) = sum_n in mathbbZ [a leq n leq b] f(n) $$



                                  When using this technique, you generally take all sums to be over all integers and use the Iverson brackets to control which terms are actually summed over. I will henceforth suppress the $in mathbbZ$.



                                  It's additionally useful to use the convention that when $P$ is false, that $[P]$ is strongly zero; that is, when P is false, we always say $[P] t = 0$ no matter what $t$ is, even when $t$ is undefined. As an example of this usage:



                                  $$ fracpi^26 = sum_n [n geq 1] frac1n^2 $$



                                  Normally we would say the right hand side is undefined, since $frac1n^2$ is undefined when $n=0$. But by the "strongly zero" convention, we say that $[n geq 1] frac1n^2$ is well-defined and zero when $n=0$, so this sum makes sense.




                                  Now, to apply it to your example:




                                  $$sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k$$




                                  $$sum_i=1^n-1sum_k=2^n-i+1
                                  = sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                  Note that $[P][Q] = [P text and Q]$. Multiplication is somewhat more convenient notation, though, so I leave it expressed as a product.



                                  One could approach this problem by finding a different way of expressing this system of inequalities. We can rewrite them as



                                  $$ 1 leq i qquad i leq n-1 qquad qquad 2 leq k qquad qquad i leq n+1-k $$



                                  The $i leq n-1$ condition is redundant. Having "solved" the last inequality for $i$ it's clear that we can rewrite



                                  $$ [1 leq i leq n-1] [2 leq k leq n-i+1] = [2 leq k] [1 leq i leq n+1-k] $$



                                  Depending on our purposes, it may help to observe the implicit $1 leq n+1-k$ constraint and solve it for $k$ to make it more explicit, so we have



                                  $$ ldots = [2 leq k leq n] [1 leq i leq n+1-k] $$



                                  It's clear now that



                                  $$ sum_i,k [2 leq k leq n] [1 leq i leq n+1-k] = sum_k=2^n sum_i=1^n+1-k $$



                                  if we really want to rewrite the summation back into this form.




                                  One way in which this notation becomes really useful, in my opinion, when you consider changing variables. If I was given



                                  $$ sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                  I would often consider simplifying the upper bound by making a substitution $j = n-i+1$ (or $i = n-j+1$), replacing the sum over $i$ with a sum over $j$



                                  $$ ldots = sum_j,k [1 leq n-j+1 leq n-1] [2 leq k leq j]
                                  \= sum_j,k [1 leq n-j+1] [n-j+1 leq n-1] [2 leq k leq j]
                                  \= sum_j,k [j leq n] [2 leq j] [2 leq k leq j]
                                  \= sum_j,k [2 leq k leq j leq n] $$



                                  which makes it easy to see other ways to rewrite this. E.g. if I wanted to sum over $k$ first, it's clear this becomes



                                  $$ ldots = sum_j,k [2 leq k leq n] [k leq j leq n]
                                  \= sum_k=2^n sum_j=k^n $$



                                  Or I could change $j$ back to $i$ first if I wanted.






                                  share|cite|improve this answer


























                                    up vote
                                    0
                                    down vote













                                    I've found the Iverson bracket extremely useful for this sort of calculation. For a reference on the technique, I learned it from Concrete Mathematics



                                    The Iverson bracket is a function whose argument is a proposition, and is defined by the formula



                                    $$ [P] = begincases 0 & P text is false \ 1 & P text is true endcases $$



                                    You use this to express summations, such as



                                    $$ sum_n=a^b f(n) = sum_n in mathbbZ [a leq n leq b] f(n) $$



                                    When using this technique, you generally take all sums to be over all integers and use the Iverson brackets to control which terms are actually summed over. I will henceforth suppress the $in mathbbZ$.



                                    It's additionally useful to use the convention that when $P$ is false, that $[P]$ is strongly zero; that is, when P is false, we always say $[P] t = 0$ no matter what $t$ is, even when $t$ is undefined. As an example of this usage:



                                    $$ fracpi^26 = sum_n [n geq 1] frac1n^2 $$



                                    Normally we would say the right hand side is undefined, since $frac1n^2$ is undefined when $n=0$. But by the "strongly zero" convention, we say that $[n geq 1] frac1n^2$ is well-defined and zero when $n=0$, so this sum makes sense.




                                    Now, to apply it to your example:




                                    $$sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k$$




                                    $$sum_i=1^n-1sum_k=2^n-i+1
                                    = sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                    Note that $[P][Q] = [P text and Q]$. Multiplication is somewhat more convenient notation, though, so I leave it expressed as a product.



                                    One could approach this problem by finding a different way of expressing this system of inequalities. We can rewrite them as



                                    $$ 1 leq i qquad i leq n-1 qquad qquad 2 leq k qquad qquad i leq n+1-k $$



                                    The $i leq n-1$ condition is redundant. Having "solved" the last inequality for $i$ it's clear that we can rewrite



                                    $$ [1 leq i leq n-1] [2 leq k leq n-i+1] = [2 leq k] [1 leq i leq n+1-k] $$



                                    Depending on our purposes, it may help to observe the implicit $1 leq n+1-k$ constraint and solve it for $k$ to make it more explicit, so we have



                                    $$ ldots = [2 leq k leq n] [1 leq i leq n+1-k] $$



                                    It's clear now that



                                    $$ sum_i,k [2 leq k leq n] [1 leq i leq n+1-k] = sum_k=2^n sum_i=1^n+1-k $$



                                    if we really want to rewrite the summation back into this form.




                                    One way in which this notation becomes really useful, in my opinion, when you consider changing variables. If I was given



                                    $$ sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                    I would often consider simplifying the upper bound by making a substitution $j = n-i+1$ (or $i = n-j+1$), replacing the sum over $i$ with a sum over $j$



                                    $$ ldots = sum_j,k [1 leq n-j+1 leq n-1] [2 leq k leq j]
                                    \= sum_j,k [1 leq n-j+1] [n-j+1 leq n-1] [2 leq k leq j]
                                    \= sum_j,k [j leq n] [2 leq j] [2 leq k leq j]
                                    \= sum_j,k [2 leq k leq j leq n] $$



                                    which makes it easy to see other ways to rewrite this. E.g. if I wanted to sum over $k$ first, it's clear this becomes



                                    $$ ldots = sum_j,k [2 leq k leq n] [k leq j leq n]
                                    \= sum_k=2^n sum_j=k^n $$



                                    Or I could change $j$ back to $i$ first if I wanted.






                                    share|cite|improve this answer
























                                      up vote
                                      0
                                      down vote










                                      up vote
                                      0
                                      down vote









                                      I've found the Iverson bracket extremely useful for this sort of calculation. For a reference on the technique, I learned it from Concrete Mathematics



                                      The Iverson bracket is a function whose argument is a proposition, and is defined by the formula



                                      $$ [P] = begincases 0 & P text is false \ 1 & P text is true endcases $$



                                      You use this to express summations, such as



                                      $$ sum_n=a^b f(n) = sum_n in mathbbZ [a leq n leq b] f(n) $$



                                      When using this technique, you generally take all sums to be over all integers and use the Iverson brackets to control which terms are actually summed over. I will henceforth suppress the $in mathbbZ$.



                                      It's additionally useful to use the convention that when $P$ is false, that $[P]$ is strongly zero; that is, when P is false, we always say $[P] t = 0$ no matter what $t$ is, even when $t$ is undefined. As an example of this usage:



                                      $$ fracpi^26 = sum_n [n geq 1] frac1n^2 $$



                                      Normally we would say the right hand side is undefined, since $frac1n^2$ is undefined when $n=0$. But by the "strongly zero" convention, we say that $[n geq 1] frac1n^2$ is well-defined and zero when $n=0$, so this sum makes sense.




                                      Now, to apply it to your example:




                                      $$sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k$$




                                      $$sum_i=1^n-1sum_k=2^n-i+1
                                      = sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                      Note that $[P][Q] = [P text and Q]$. Multiplication is somewhat more convenient notation, though, so I leave it expressed as a product.



                                      One could approach this problem by finding a different way of expressing this system of inequalities. We can rewrite them as



                                      $$ 1 leq i qquad i leq n-1 qquad qquad 2 leq k qquad qquad i leq n+1-k $$



                                      The $i leq n-1$ condition is redundant. Having "solved" the last inequality for $i$ it's clear that we can rewrite



                                      $$ [1 leq i leq n-1] [2 leq k leq n-i+1] = [2 leq k] [1 leq i leq n+1-k] $$



                                      Depending on our purposes, it may help to observe the implicit $1 leq n+1-k$ constraint and solve it for $k$ to make it more explicit, so we have



                                      $$ ldots = [2 leq k leq n] [1 leq i leq n+1-k] $$



                                      It's clear now that



                                      $$ sum_i,k [2 leq k leq n] [1 leq i leq n+1-k] = sum_k=2^n sum_i=1^n+1-k $$



                                      if we really want to rewrite the summation back into this form.




                                      One way in which this notation becomes really useful, in my opinion, when you consider changing variables. If I was given



                                      $$ sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                      I would often consider simplifying the upper bound by making a substitution $j = n-i+1$ (or $i = n-j+1$), replacing the sum over $i$ with a sum over $j$



                                      $$ ldots = sum_j,k [1 leq n-j+1 leq n-1] [2 leq k leq j]
                                      \= sum_j,k [1 leq n-j+1] [n-j+1 leq n-1] [2 leq k leq j]
                                      \= sum_j,k [j leq n] [2 leq j] [2 leq k leq j]
                                      \= sum_j,k [2 leq k leq j leq n] $$



                                      which makes it easy to see other ways to rewrite this. E.g. if I wanted to sum over $k$ first, it's clear this becomes



                                      $$ ldots = sum_j,k [2 leq k leq n] [k leq j leq n]
                                      \= sum_k=2^n sum_j=k^n $$



                                      Or I could change $j$ back to $i$ first if I wanted.






                                      share|cite|improve this answer














                                      I've found the Iverson bracket extremely useful for this sort of calculation. For a reference on the technique, I learned it from Concrete Mathematics



                                      The Iverson bracket is a function whose argument is a proposition, and is defined by the formula



                                      $$ [P] = begincases 0 & P text is false \ 1 & P text is true endcases $$



                                      You use this to express summations, such as



                                      $$ sum_n=a^b f(n) = sum_n in mathbbZ [a leq n leq b] f(n) $$



                                      When using this technique, you generally take all sums to be over all integers and use the Iverson brackets to control which terms are actually summed over. I will henceforth suppress the $in mathbbZ$.



                                      It's additionally useful to use the convention that when $P$ is false, that $[P]$ is strongly zero; that is, when P is false, we always say $[P] t = 0$ no matter what $t$ is, even when $t$ is undefined. As an example of this usage:



                                      $$ fracpi^26 = sum_n [n geq 1] frac1n^2 $$



                                      Normally we would say the right hand side is undefined, since $frac1n^2$ is undefined when $n=0$. But by the "strongly zero" convention, we say that $[n geq 1] frac1n^2$ is well-defined and zero when $n=0$, so this sum makes sense.




                                      Now, to apply it to your example:




                                      $$sum_i=1^n-1sum_k=2^n-i+1tosum_k=2^nsum_i=1^n+1-k$$




                                      $$sum_i=1^n-1sum_k=2^n-i+1
                                      = sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                      Note that $[P][Q] = [P text and Q]$. Multiplication is somewhat more convenient notation, though, so I leave it expressed as a product.



                                      One could approach this problem by finding a different way of expressing this system of inequalities. We can rewrite them as



                                      $$ 1 leq i qquad i leq n-1 qquad qquad 2 leq k qquad qquad i leq n+1-k $$



                                      The $i leq n-1$ condition is redundant. Having "solved" the last inequality for $i$ it's clear that we can rewrite



                                      $$ [1 leq i leq n-1] [2 leq k leq n-i+1] = [2 leq k] [1 leq i leq n+1-k] $$



                                      Depending on our purposes, it may help to observe the implicit $1 leq n+1-k$ constraint and solve it for $k$ to make it more explicit, so we have



                                      $$ ldots = [2 leq k leq n] [1 leq i leq n+1-k] $$



                                      It's clear now that



                                      $$ sum_i,k [2 leq k leq n] [1 leq i leq n+1-k] = sum_k=2^n sum_i=1^n+1-k $$



                                      if we really want to rewrite the summation back into this form.




                                      One way in which this notation becomes really useful, in my opinion, when you consider changing variables. If I was given



                                      $$ sum_i,k [1 leq i leq n-1] [2 leq k leq n-i+1] $$



                                      I would often consider simplifying the upper bound by making a substitution $j = n-i+1$ (or $i = n-j+1$), replacing the sum over $i$ with a sum over $j$



                                      $$ ldots = sum_j,k [1 leq n-j+1 leq n-1] [2 leq k leq j]
                                      \= sum_j,k [1 leq n-j+1] [n-j+1 leq n-1] [2 leq k leq j]
                                      \= sum_j,k [j leq n] [2 leq j] [2 leq k leq j]
                                      \= sum_j,k [2 leq k leq j leq n] $$



                                      which makes it easy to see other ways to rewrite this. E.g. if I wanted to sum over $k$ first, it's clear this becomes



                                      $$ ldots = sum_j,k [2 leq k leq n] [k leq j leq n]
                                      \= sum_k=2^n sum_j=k^n $$



                                      Or I could change $j$ back to $i$ first if I wanted.







                                      share|cite|improve this answer














                                      share|cite|improve this answer



                                      share|cite|improve this answer








                                      edited Aug 28 at 15:33

























                                      answered Aug 28 at 15:28









                                      Hurkyl

                                      109k9113254




                                      109k9113254



























                                           

                                          draft saved


                                          draft discarded















































                                           


                                          draft saved


                                          draft discarded














                                          StackExchange.ready(
                                          function ()
                                          StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fmath.stackexchange.com%2fquestions%2f1876828%2fhow-to-change-the-order-of-summation%23new-answer', 'question_page');

                                          );

                                          Post as a guest













































































                                          這個網誌中的熱門文章

                                          tkz-euclide: tkzDrawCircle[R] not working

                                          How to combine Bézier curves to a surface?

                                          Kubernetes: automatically remove old custom resource definitions